Tuesday, June 23, 2009

More gyprock, More electrical ducting




Nothing too exciting to report. The past days have really been the domain of the plasters and electricians. They are taking up quite a bit of room in the house. Their progress can be seen in the pictures. A large platform has been erected in the master bedroom so that the fitting of the new ceiling boards can take place. This will be very nice, because we will now cover the horrible nicotine, smoke damaged ceiling that currently exists.

The main ensuite is boarded with waterproof boards, so that is looking pretty fine.

Tomorrow is the weekly meeting of the project manager on site with us, and that is always fun. Andi is doing a good job, so we need to ensure momentum is maintained.