Monday, May 25, 2009

Builders nearing completion



Well.  Into the third building week, and things have really moved along.  We have doorways in places that there previously wasn't any, and we have walls were there were doorways. Our key structural changes are complete.  

We have agreed who will build the new chimney and fireplace, and on Wednesday we have a serious planning session with Urs and Andi.  We are certain that the budget monster will raise its' head.

The builders should complete their tasks by mid-week, and then should come the carpenter and under-floor heating specialist.  

Last Wednesday we placed the order for the new windows and frames, as well as a number of fly screens.  Living next door to a horse stable will require some protection.

We also measured up for the new sliding three panel door for the rear of the house.  The brother of Regina is about to furnish us a quote to replace the concrete slab which comprises the roof of the garage.

All in all.  A solid work period.