Sunday, September 13, 2009

No pics, but a report

Saturday 12th September. The plasterers have finished, and the window sills are finished. The rooms are now cleaned and the house awaits the arrival of the painter.

On Friday the front door was taken away to be cut down, the back door will be taken away on Monday for the same.

The pointing of the main wall is mostly complete and looks very nice.

Today, Sunday, we will spend some time measuring our current wardrobes, and try to establish which ones fit where.

Here is a short list of what needs to be completed:-

1. Electrical fittings to be completed including main power board.
2. Ceilings and walls to be painted.
3. Upper walls and doors to be constructed and fitted. 2nd Floor.
4. Parquet to be laid
5. Kitchen to be fitted.
6. Front and rear doors to be refitted, and lacquered.
7. Pointing to be completed.
8. Bitumen to laid on the garage roof.